Owner: City of Virginia Beach
Engineer: Michael Baker
Contract Value: $48,759,442
Project Completed: August 1997
Details: 49.9 miles of 60'' pipe
(167,910 LF 60'' PCCP and 95,454 LF 60'' DIP)
Excerpt from Price Brothers Company Pipesite: "More than 40 miles of the pipeline followed a wide and well-elevated right-of-way formerly used for a railroad line. It was possible for the highly trained and organized John D. Stephens, Inc. crew to install as many as 70 sections of PCCP a day under these ideal conditions. "